Propagation and conflicts

When you move, resize or link a task, the tasks that depend on it should follow. Propagation is the step that works out how. This page explains what moves and what does not, how the chart walks the links, what a conflict is and where it is reported, and how to get plain moves with no propagation at all.

  • A drag or an updateTask call becomes new dates for one task. Propagation then moves the tasks linked to it, and the children pinned to it. The result is one ChangeSet.
  • A link is rigid: it keeps its lag, in both directions in time. Move the predecessor later or earlier and the successor follows.
  • Propagation never refuses an edit. If the result breaks a rule (a bar on a day off, a child outside its parent, a link whose gap is too small), the ChangeSet carries a conflict, and your before-hook decides what to do.
  • Only dates propagate. A change of progress touches its own task and no other.
  • It is on by default. scheduling.propagation: 'none' turns off the links, and hierarchy.moveChildren: 'none' turns off the children.
Related task Moves when the edited task moves?
A successor along a link of any type Yes, keeping the link’s lag. Only an edge that changed moves its dependents.
A predecessor No. Editing a task never pushes its predecessors. A gap that becomes too small is a conflict.
A child that has followParent: true Yes, by the edges of its parentAnchor.
Any other child, with moveChildren: 'all' Yes, when the parent’s start changes: the child keeps its offset from it.
The parent of the edited task No. A child that sticks out of its parent is an outside-parent conflict.
A milestone Yes, like any task; it stays a point. It cannot be resized.
A task with locked: true Never. It also stops propagation: nothing beyond it is moved on its account.
A row without a bar (placeholder, invalid task) Never, and it stops propagation. Links to it are inactive (an inactive-link issue).
A task with fixedDuration: true Moves, keeping its length. It cannot be resized and never stretches between two pins.

Propagation also follows a changed task onward: when a link moves build, build’s own successors and children move too, each task at most once.

Option Values Default What it decides
scheduling.propagation 'preserve-lag' | 'none' 'preserve-lag' Whether edits travel along links. 'push-forward' is reserved (see below).
hierarchy.moveChildren 'all' | 'following' | 'none' 'all' Which children move with a moved parent: all, only those with followParent, or none.
hierarchy.childAnchor a link type, or a list of them 'SS' The default parentAnchor of a child with followParent: which edges are pinned to the parent’s.
scheduling.skipNonWorkingDays { move, resize, progress } booleans { move: true, resize: false, progress: true } Whether the edited edge of a drag skips days off. updateTask never does.
scheduling.durationMode 'calendar' | 'working' 'calendar' Whether lengths and lags count all time or working time. task.durationMode overrides it.
scheduling.keepDayPrecision boolean true Whether a day-precision task stays on whole days when edited.

Some fields of tasks and links take part as well:

Field Effect
task.locked Not editable, not moved, and a wall for propagation.
task.fixedDuration Keeps its length when pushed; cannot be resized.
task.followParent, task.parentAnchor Pin the child to its parent’s edges, see Hierarchy.
task.type: 'milestone' A point: zero length, cannot be resized.
link.type, link.lag Which edges are joined and the gap kept, see Links and types.

The granularity and alignInput apply too: every date in the result is a multiple of the granularity, see Granularity and alignment.

Take four tasks and three links. Design, Build and Test are in a chain; Docs starts a week after Design starts.

import { createGantt } from '@ganttlane/dom';
const gantt = createGantt(container, {
tasks: [
{ id: 'design', name: 'Design', start: '2026-03-02', end: '2026-03-06' }, // Mon to Fri
{ id: 'build', name: 'Build', start: '2026-03-09', end: '2026-03-13' },
{ id: 'test', name: 'Test', start: '2026-03-16', end: '2026-03-18' },
{ id: 'docs', name: 'Docs', start: '2026-03-09', end: '2026-03-11' },
],
links: [
// Finish-to-start with no lag: keeps the gap the data has now, the weekend.
{ source: 'design', target: 'build' },
// Finish-to-start with a lag: Test starts two days after Build ends.
{ source: 'build', target: 'test', lag: 2 },
// Start-to-start with a lag: Docs starts seven days after Design starts.
{ source: 'design', target: 'docs', type: 'SS', lag: 7 },
],
onTasksChange: (changeSet) => console.log(changeSet),
});
// Move Design one week later.
await gantt.updateTask('design', { start: '2026-03-09' });

One tasksChange fires. Its ChangeSet has all four tasks, the edited one first and the others in topological order (the table gives the first and the last day of each bar):

Task Cause via Before After
design 'direct' Mar 2 to Mar 6 Mar 9 to Mar 13
build 'link' design Mar 9 to Mar 13 Mar 16 to Mar 20
test 'link' build Mar 16 to Mar 18 Mar 23 to Mar 25
docs 'link' design Mar 9 to Mar 11 Mar 16 to Mar 18

In the ChangeSet itself the dates are the core’s floating numbers, and endExclusive is the first moment after the bar:

{
reason: 'api',
changes: [
{
id: 'design',
cause: 'direct',
before: { start: 1772409600000, endExclusive: 1772841600000, progress: 0 }, // Mar 2, Mar 7
after: { start: 1773014400000, endExclusive: 1773446400000, progress: 0 }, // Mar 9, Mar 14
},
{
id: 'build',
cause: 'link',
via: 'design', // the predecessor whose link placed it
before: { start: 1773014400000, endExclusive: 1773446400000, progress: 0 },
after: { start: 1773619200000, endExclusive: 1774051200000, progress: 0 },
},
// ... test, docs
],
conflicts: [], // Nothing is on a day off or outside a parent, and no link is short.
}

Step by step, this is what happened:

  1. The edited task gets its new dates. From a drag they are already snapped; from updateTask they are exact (aligned to the granularity, never rolled onto working days). An unknown task, a task without a bar, a locked task or an edit that changes nothing gives an empty ChangeSet, and nothing is committed.
  2. The direction is decided. An edit is forward when either edge moves later, and backward otherwise. It matters when several links hit the same edge, and for rounding ties.
  3. The reachable tasks are collected and sorted. The chain is followed from predecessors to successors over active links that are not on a cycle, and from parents to children according to moveChildren. The tasks are put in topological order, ties in the order of your tasks array. Each task is visited at most once, so a cycle cannot loop.
  4. Each task collects pins. A link pins the edge of the successor that its type names (FS and SS the start, FF and SF the end) at the predecessor’s new edge plus the lag. A parent pins the edges of a following child at its own new edge plus the child’s old offset. When several pins hit the same edge, the one furthest in the direction of the edit wins.
  5. The task is placed. Only the start pinned: it moves there and keeps its length. Only the end pinned: it moves so that it ends there. Both pinned (an SS and an FF link from the same predecessor, or a parentAnchor with two edges): it is placed between the pins, so its length can change, unless it is a milestone or fixedDuration. An FS and an FF link with no lags both hang from the predecessor’s end, so the task keeps its length. The new edges are aligned to the granularity, and in working mode rolled onto working time.
  6. Nothing changed means nothing follows. If the new bounds equal the old ones, the task is not in the ChangeSet and moves nothing else. This is why resizing the start of a task leaves its FS successors alone, and moves its SS successors.
  7. Progress is rebased. A task whose length changed keeps either the done part (progressAnchor: 'start', the default) or the remainder ('end'). A task that only moved keeps its percentage.
  8. Conflicts are collected for the result, see below.

A task can be pinned twice on the same edge: by two links, or by a link and by its parent. The pin furthest in the direction of the edit wins: the latest after a forward edit, the earliest after a backward one. After a forward edit this keeps a successor from being left behind by a predecessor that moved later. On equal times the parent’s pin wins over the links, and among links the first one read wins (your links array, then task.dependencies). After a backward edit another link of the task can end up short, and that is reported as a link-violated conflict.

A link with a lag puts the successor exactly that far from its predecessor after every propagation, not at least that far. A link without a lag keeps the gap the data has when it is read, measured in the successor’s durationMode. getLink(id).lag shows the result as { ms, days, mode, derived }, and derived is true for a measured gap.

Data whose gaps do not match the lags you wrote will jump on the first propagation. Write the dates that the lag implies, or leave the lag out.

A conflict is a warning about the state of the plan. It never blocks anything: the chart does not refuse, move or correct a bar because of it. It is information for your before-hook, your UI and your users.

type Meaning Fields besides type, severity ('warning'), id, message
'non-working-start' The bar starts on a non-working day. date: midnight of that day.
'non-working-end' The last day of the bar is a non-working day. date
'outside-parent' The bar starts before its parent or ends after it. parentId, edges: 'start', 'end' or both.
'link-violated' A link’s gap is below the minimum it requires. linkId, requiredMs, actualMs. id is the link’s target.

id is the task the conflict is shown on. A milestone has only a start. For an outside-parent conflict, parentId is the parent that has a bar. The minimum gap of a link-violated conflict is the link’s lag when it has one, and min(measured lag, 0) when it does not, so a link without a lag conflicts only when the successor overlaps its predecessor more than it did when the data was read.

Where What it holds
ChangeSet.conflicts The conflicts of the result that involve a task the edit changed, and no others. Delivered with tasksChange.
BeforeTaskChangeContext.conflicts The same list, so a hook can answer before the commit. See Change sets and hooks.
TaskRecord.conflicts The conflicts of the committed data, for every task, including those that were in your data from the start.
SessionChanges.conflicts The conflicts of the state that an edit session’s changes lead to.
data-conflict on bars and arrows The default theme outlines a bar and an arrow in conflict, with --gantt-bar-conflict-color and --gantt-link-conflict-color.

There is no conflict event. Read changeSet.conflicts in onTasksChange.

A conflict can exist before anyone drags anything. A task that starts on a Saturday, a child that begins before its parent, or a link whose gap is shorter than its lag is a conflict in TaskRecord.conflicts as soon as the data is loaded. A drag can create new ones, and it can fix old ones: moving a bar off a Saturday removes its non-working-start.

A link without a lag is the subtle case. Its minimum comes from the gap measured when the data was read, so each time the model is rebuilt (after a committed change in uncontrolled mode, or after setTasks) the current gap becomes the new baseline. The ChangeSet of the edit that shortened the gap carries the link-violated conflict, so a hook sees it. The records read afterwards do not show it, because the shortened gap is now what the data says. Give the link a lag when the gap is a rule.

Two more things to know about timing:

  • A drag has no conflicts while it is in progress. The preview moves the bars live but skips the check, to stay fast. The conflicts are computed once, when the drag is committed.
  • Backward edits can short a link from a task that did not move. Propagation follows changed tasks only. Pull a task earlier and it can end up before another, unchanged predecessor. That is reported as link-violated, not fixed.

scheduling.propagation: 'push-forward' is not available yet. The value is accepted, it reports an unsupported-option issue (path: 'scheduling.propagation', suggested: 'preserve-lag'), and the chart behaves as 'preserve-lag'. Any other value that is not 'preserve-lag' or 'none' is an invalid-option issue, and the default is used. See Issues.

const issues = gantt.setOptions({ scheduling: { propagation: 'push-forward' } });
// [{ code: 'unsupported-option', severity: 'error', path: 'scheduling.propagation',
// value: 'push-forward', suggested: 'preserve-lag', message: '...' }]

While the pointer is down, each new snapped position runs the propagation again and the chart shows the result as a draft over your data: the bar and its successors move live, and the tooltip shows the previewed dates. getTask(id) still returns the committed values, and getBarRect(id) returns where the bar is drawn. Nothing is emitted, and no hook runs.

On release the computation runs once more at the final position. The result is re-validated (aligned, conflicts computed), shown to onBeforeTaskChange, and, if allowed, committed as one change. Escape during the drag cancels it and nothing is committed.

updateTask takes the same path with two differences. Its values are exact: no snapping to the view mode’s step and no rolling onto working days. And it has no preview, since nothing is being dragged.

For plain moves, where only the dragged task changes, switch off both the links and the children:

import { createGantt } from '@ganttlane/dom';
const gantt = createGantt(container, {
tasks,
links,
scheduling: { propagation: 'none' },
hierarchy: { moveChildren: 'none' },
});
// It can be changed at any time, without recreating the chart.
gantt.setOptions({ scheduling: { propagation: 'preserve-lag' } });

With propagation: 'none' the links are still drawn, and a move that breaks one reports a link-violated conflict.

To decide per gesture instead of globally, let the hook keep only the edited task. The replacement is re-validated like any other, and the conflicts are recomputed for it:

const gantt = createGantt(container, {
tasks,
links,
onBeforeTaskChange: ({ changeSet }) => ({
...changeSet,
changes: changeSet.changes.filter((change) => change.cause === 'direct'),
}),
});

To pin one task in place, set locked: true on it. Then it cannot be edited either.

  • Predecessors are not pushed. Dragging a successor earlier than its predecessor ends is allowed and reported as a conflict, not prevented. Cancel it in the hook if you want a hard rule.
  • A locked task cuts the chain. Tasks behind a locked one do not move for an edit before it, even though they are linked.
  • A cycle in the data takes its links out of propagation. They are drawn in the conflict colour and reported as a cycle issue. A link the user draws that would close a cycle is refused.
  • editing: false does not stop propagation. It turns off gestures from the UI. updateTask still propagates.
  • The check is per edit. Conflicts that your data already has, and that the edit did not touch, are not in the ChangeSet. Read them from TaskRecord.conflicts.