Working days at one-hour granularity

A Monday-to-Friday calendar with a named holiday, tasks timed to the hour, and a before-hook that asks before a bar lands on a day off. Three settings make it work:

  • calendar says which days are working days;
  • scheduling.granularity: '1h' makes the data step one hour: every date, duration and lag in the chart is a whole number of hours (10:30 is reported as misaligned and aligned);
  • durationMode: 'working' counts a duration in working time only, so a task of two working days that starts on Thursday at 10:00 ends on Monday at 10:00 (the weekend is skipped, the time of day is kept).
Terminal window
pnpm add @ganttlane/dom # vanilla
pnpm add @ganttlane/react react react-dom # React
View on GitHub
data.ts
import type { Link, Task } from '@ganttlane/core';
// Dates with a time are wall-clock time: `'2026-03-05T10:00'` is 10:00 for every viewer, in every
// time zone. 2026-03-04 is a Wednesday.
export const tasks: Task[] = [
// 8 hours: Wednesday 09:00 to 17:00.
{ id: 'freeze', name: 'Code freeze', start: '2026-03-04T09:00', duration: '8h' },
// Thursday 10:00 + 2 working days = Monday 10:00 (the weekend is skipped, the time of day kept).
{ id: 'qa', name: 'QA pass', start: '2026-03-05T10:00', duration: '2d' },
// 4 hours: Monday 10:00 to 14:00.
{ id: 'release', name: 'Release', start: '2026-03-09T10:00', duration: '4h' },
// Monday 15:00 + 2 working days, with Tuesday a holiday = Thursday 15:00.
{ id: 'monitor', name: 'Monitor', start: '2026-03-09T15:00', duration: '2d' },
];
export const links: Link[] = [
// No lag: QA keeps the gap the data has, 17 hours from Wednesday 17:00 to Thursday 10:00.
// Drag the freeze an hour later and QA follows by an hour.
{ source: 'freeze', target: 'qa' },
{ source: 'qa', target: 'release' },
// A lag is a rule instead: Monitor starts an hour after the release ends, wherever it goes.
{ source: 'release', target: 'monitor', lag: '1h' },
];

Files

  • data.ts: four tasks timed to the hour, and the links with their lags.
  • options.ts: the calendar, the scheduling rules, display, and two handlers.
  • helpers.ts: describe, which reads a task’s computed record.
  • vanilla.ts and react.tsx: the chart and the view mode buttons.

Options

Option Value What it does
calendar.weekends [0, 6] Sunday and Saturday are days off (the default)
calendar.holidays [{ date, name }] A named day off; the name shows when hovering the day
scheduling.granularity '1h' The data step: one hour
scheduling.durationMode 'working' Durations count working time only
scheduling.skipNonWorkingDays { move: true, resize: true } Drags land on working days
display.nonWorkingDays 'stripes' Days off are striped ('fill' is the default)
viewMode 'quarter-day' 6-hour columns; the buttons switch to 'day' and 'hour'
onBeforeTaskChange a function Asks before a bar ends up on a day off; false cancels, a promise works too
onIssues a function Reports problems with the data or the options

What to try

Drag Code freeze an hour later and QA follows by an hour. Drag QA onto the weekend: the before-hook asks. The line under the chart says where QA is, from its computed record. Hold Alt while dragging to snap to the data step (one hour here) instead of the view mode’s.

Notes

  • The dates are floating wall-clock time: '2026-03-05T10:00' is 10:00 for every viewer, in every time zone. Strings with Z or an offset are rejected.
  • A task given as a bare date ('2026-03-06') has day precision and stays on whole days even at an hourly granularity (scheduling.keepDayPrecision, on by default); give it a time to make it a timed task.
  • A drag snaps to the step of the view mode (scheduling.snap overrides it): 1h in the quarter-day mode used here. A step finer than the granularity (the hour mode’s 15 minutes) is raised to the granularity by itself.
  • A working day is the whole 24 hours; working hours (shifts) are not modelled yet. So a gap in working time counts the night between Wednesday 17:00 and Thursday 10:00 (17 hours) and skips the weekend.
  • A link without a lag keeps the gap it has now. A lag (a number of days, or a duration such as '1h') is a rule, not a minimum: after a drag the successor sits exactly that far from its predecessor, so give dates that already do. If Monitor started at 18:00 here, the first drag of Release would pull it back to one hour after Release ends.
  • The records are computed from the calendar: gantt.getTask('qa') has Dates with the wall-clock time the data says, and duration.workingDays.