Links and link types

A Link ties an edge of one task to an edge of another. It is drawn as an arrow, it moves the successor when you edit the predecessor (unless scheduling.propagation is 'none'), and it reports a conflict when the gap between the two gets too small. After this page you can choose a link type, express a gap or an overlap, write links in either of the two forms, and read what the chart says about links it could not use.

import { createGantt } from '@ganttlane/dom';
createGantt(container, {
tasks: [
{ id: 'design', name: 'Design', start: '2026-03-02', end: '2026-03-06' },
{ id: 'build', name: 'Build', start: '2026-03-09', duration: 10 },
],
links: [{ source: 'design', target: 'build' }], // finish-to-start, no lag
});

source is the predecessor and target the successor. They are the only required fields:

Field Type Default Meaning
source string | number required The predecessor: the id of a task
target string | number required The successor: the id of a task
type 'FS' | 'SS' | 'FF' | 'SF' scheduling.defaultLinkType ('FS') Which edges the link ties together
lag number | string | object the gap the data has now The gap the link keeps between the two edges
id string source:type:target, for example design:FS:build Unique id of the link
editable boolean true false keeps the link menu from removing the link

source and target are compared with === against the task ids, so keep them in the form of the id they name (5 and '5' are different tasks).

A link does not move anything when the data loads. Your dates are taken as they are; the link starts to act when a task is edited, and it flags a gap that is too small as a conflict.

The four types differ in which edge of the predecessor is tied to which edge of the successor. An “end” here is the exclusive end of the bar: the moment it stops.

Type Predecessor edge Successor edge In words
FS end start The successor starts when the predecessor ends
SS start start They start together
FF end end They finish together
SF start end The successor finishes when the predecessor starts
FS A [=======]
B [====] B.start = A.end + lag
SS A [=======]
B [====] B.start = A.start + lag
FF A [=======]
B [===] B.end = A.end + lag
SF A [=======]
B [===] B.end = A.start + lag

FS is the common case and the default. Change the default for every link that names no type with scheduling.defaultLinkType.

Two links of different types between the same pair are allowed, and together they tie both edges of the successor. An SS and an FF link make the successor stretch when the predecessor is resized. An FS and an FF link both hang from the predecessor’s end, so with no lags the successor moves as a whole instead. Two links with the same source, target and type are duplicates (see below).

The link types example draws all four, and the propagation example shows what an edit does to each.

The lag is the gap between the linked edges, measured from the predecessor’s edge to the successor’s edge. A positive lag is a gap; a negative lag is a lead, an overlap.

lag An FS link means
not given Keep the gap the data has now
0 The successor starts the moment the predecessor ends
2 or '2d' Two days between them
-1 The successor starts a day before the predecessor ends
'4h' Four hours (needs a sub-day granularity)
0.5 Half a day, twelve hours (needs a sub-day granularity too)

How a lag is written:

  • A number is days. Negative numbers are leads: -1, -0.5.
  • A string or an object is a duration: '4h', '1d 4h', { days: 1, hours: 4 }. These cannot be negative, so write a lead as a negative number of days. The units are in Dates and time.
  • Months, quarters and years are not allowed in a lag ('1mo'): the link is dropped with an invalid-duration issue.
  • A lag is counted in the successor’s durationMode: calendar time by default, working time for a successor with durationMode: 'working'. There is no separate lag mode. See The work calendar.
  • A lag is a multiple of the granularity. One that is not is rounded to the nearest multiple (a tie goes up) with a misaligned warning, or, with alignInput: 'reject', the link is dropped.

A lag is a rule, a missing lag is a memory

Section titled “A lag is a rule, a missing lag is a memory”

An edit puts the successor exactly at the lag from the predecessor, not at least that far. With no lag, the chart measures the gap in your data when it loads and keeps that gap, in both directions:

const tasks = [
{ id: 'a', name: 'A', start: '2026-03-02', end: '2026-03-04' }, // ends at the start of Mar 5
{ id: 'b', name: 'B', start: '2026-03-09', end: '2026-03-10' }, // starts Mar 9: a 4-day gap
];
const gantt = createGantt(container, { tasks, links: [{ source: 'a', target: 'b' }] });
gantt.getLink('a:FS:b')?.lag; // { ms: 345600000, mode: 'calendar', derived: true, days: 4 }
await gantt.updateTask('a', { start: '2026-03-03' }); // a moves one day later
gantt.getTask('b')?.start; // Tue Mar 10: b followed, the gap is still 4 days

Give a lag when the gap is a rule of the plan. If the data already has a different gap, the first edit pulls the successor to the lag, so write dates that agree with it. A gap smaller than an explicit lag is reported as a link-violated conflict on the successor, with requiredMs and actualMs. Without a lag, only an overlap that the successor did not already have at load is flagged.

So lag on a link record is the gap the link keeps, not always the gap the bars have: an explicit one stays what you wrote after a drop that breaks it, and no record follows a drag in progress. The link gaps in a tooltip example measures the gap between the bars instead.

The array is the canonical form. Each entry is a Link you own: it can carry an id of your choosing and editable: false, and the links a user draws are appended to it (in controlled data, you append them: see Data ownership).

A task can list its predecessors itself. The entry is the id of the predecessor, or an object with the optional type and lag:

const tasks = [
{ id: 'design', name: 'Design', start: '2026-03-02', end: '2026-03-06' },
{ id: 'build', name: 'Build', start: '2026-03-09', duration: 10 },
{
id: 'ship',
name: 'Ship',
start: '2026-03-19',
duration: 1,
// design -> ship as finish-to-start, and build -> ship as finish-to-finish with a day of lag
dependencies: ['design', { id: 'build', type: 'FF', lag: 1 }],
},
];

The entry names the source; the task that lists it is the target. Both forms end up in the same graph:

  • The list is links first, in array order, then each task’s dependencies, in task order.
  • A shorthand link always gets the default id (design:FS:ship); you cannot name it, and it cannot be editable: false.
  • The same default id used twice drops the later link with a duplicate-id error, also between the two forms. Two links with different ids but the same source, target and type are a duplicate-link.
  • gantt.getLink(id) finds a link from either form. A link from the shorthand has no Link of its own: its record’s model.link is undefined.
  • Deleting a shorthand link in uncontrolled data removes the entry from the target’s dependencies (the chart replaces that task object). In React with controlled links, such a deletion is reported by onLinkDelete only, because there is no entry in links to remove.

Use the shorthand for data that arrives with its dependencies on each task, and the array when people draw and delete links, because the array is what a controlled owner can keep in sync.

gantt.getLink(id) returns a LinkRecord, or undefined for an unknown or dropped id.

Field Meaning
id, source, target, type, editable The link, with the defaults filled in
active true when both tasks have a bar. false for a link that touches a task without one
lag { ms, mode, derived, days }: the gap in milliseconds of the successor’s mode time. derived is true when you gave no lag. Absent on an inactive link without a lag
inCycle true when the link is on a cycle (always false when inactive)
issues The link’s own issues: inactive-link or cycle
model The normalized link: model.link is your Link, model.path says where it came from

An inactive link is kept as data but is neither drawn nor scheduled: a placeholder or an invalid task has no bar to attach to. It becomes active when the task gets one. A link to a task hidden by a collapsed parent is active and scheduled, but not drawn (see Hierarchy).

Bad links never throw. The chart drops them or marks them, and says so.

Issue Severity What happened The link
unknown-link-task error source or target matches no task (one issue per missing end, with the id in value) dropped
self-link error source and target are the same task dropped
duplicate-id error The link id (also a default id) is used again the later one is dropped
duplicate-link error Same source, target and type as an earlier link, under another id the later one is dropped
invalid-shape error Not a link: a missing source, a type that is not one of the four, … dropped
invalid-duration error A lag that is not a number or a valid duration, or one with months dropped
misaligned warning A lag off the granularity, rounded. With alignInput: 'reject' an error corrected, or dropped on 'reject'
inactive-link warning The source or the target has no bar kept, inactive
cycle error Links form a cycle kept and drawn, ignored by scheduling

Where to read them: gantt.getIssues().data and onIssues (with source: 'data') list every issue; the record of a link carries its own inactive-link or cycle; an issue has path (links[3] or tasks[5].dependencies[0]), linkId and, for the shorthand, the taskId that listed it. The issues page explains the shape of an issue.

Tasks that depend on each other in a loop (a to b to c to a) cannot be scheduled. The chart finds every cycle in the links between tasks that have bars, whatever their types. Each cycle is one issue that lists its tasks and its links:

gantt.getIssues().data.find((issue) => issue.code === 'cycle');
// { code: 'cycle', severity: 'error', taskIds: ['a', 'b', 'c'],
// linkIds: ['a:FS:b', 'b:FS:c', 'c:FS:a'], message: '...' }

The links of a cycle stay in the data and are drawn (with data-cycle on the arrow), but an edit does not travel along them: record.inCycle is true and the rest of the graph is scheduled as usual. A link that would close a cycle is refused when a user draws it or you call addLink, whatever a hook answers.

Users draw a link by dragging from the handle at the edge of a bar to another bar, or by clicking a handle and then the target. The link is { source, target, type } with the type from scheduling.defaultLinkType and no lag, so it keeps the gap the two bars have at that moment. It goes through the onBeforeLinkCreate hook, which can cancel it and is told when it would close a cycle. A click on an arrow selects the link and opens the link menu, which removes it.

  • A task with linkable: false, or a chart with editing: { links: false } (or editing: false), shows no link handles. Dropping a link on such a task is refused and reported by onEditRefused, as are a link to the same task, a duplicate and a link that would close a cycle.
  • editable: false on a link only hides the Remove action of the link menu. removeLink(id) from code still deletes it.
  • From code, addLink(link) and removeLink(id) return a result: created or deleted, or rejected with a reason (invalid, unknown-task, duplicate, cycle, unknown-link).

The events and hooks are described on the events and methods pages, and the hook and change flow in Change sets and hooks.