Change sets and before-hooks

Every change to the schedule, a drag or an API call, is described by one ChangeSet: the tasks it changed, their values before and after, and the conflicts of the result. This page covers its shape, when it is delivered, and the two before-hooks, onBeforeTaskChange and onBeforeLinkCreate, which let your code allow, cancel or rewrite a change before it is committed.

interface ChangeSet {
readonly reason: ChangeReason; // what produced it
readonly changes: readonly Change[]; // the edited task first, then the others
readonly conflicts: readonly Conflict[]; // see Propagation and conflicts
}
interface Change {
readonly id: TaskId;
readonly before: TaskPatch; // from the model, before the edit
readonly after: TaskPatch; // always different from `before`
readonly cause: 'direct' | 'link' | 'parent'; // why this task changed
readonly via?: TaskId; // the predecessor or parent that placed it; absent for 'direct'
}
interface TaskPatch {
readonly start: DateTimeMs;
readonly endExclusive: DateTimeMs; // the first moment after the bar
readonly progress: number; // percent, 0 to 100
readonly precision?: 'day' | 'time'; // only in a change that alters it
}

Two fields say where a change comes from:

  • reason says what produced the whole change set.
  • cause says why each task is in it.
reason Produced by
'move' Dragging the whole bar
'resize-start', 'resize-end' Dragging an edge
'progress' Dragging the progress handle
'api' updateTask
'undo', 'redo' undo() and redo()
'session' The aggregate of an edit session (SessionChanges)
'rollback' The inverse that a rolled-back session reverts (SessionChanges)
cause Meaning
'direct' The task was edited. Every change set has one, and it is first.
'link' A predecessor moved it through a link. via is that predecessor.
'parent' Its parent moved it. via is the parent.

The values are the core’s floating numbers: milliseconds counted as if the wall-clock time were UTC. A change set can be handed back to the core (a hook’s answer, patchTasks) without conversion. To read one as a Date use toDate from @ganttlane/core, which gives the wall-clock time as a local Date:

import { toDate } from '@ganttlane/core';
for (const { id, before, after, cause } of changeSet.changes) {
console.log(id, cause, toDate(before.start), '->', toDate(after.start), `${after.progress}%`);
}

Dates in a change set are always multiples of scheduling.granularity, and whole days for day-precision tasks. A change set is deeply frozen: copy what you want to change.

precision appears only when a change turns a day-precision task into a timed one, which scheduling.keepDayPrecision: false allows. Then before.precision is 'day' and after.precision is 'time', and an undo swaps them.

SessionChanges is a ChangeSet with one more field, links, and it comes from an edit session: the net difference between the data at begin() and now. Its reason is 'session' (from commit() and getChanges()) or 'rollback' (the inverse, from rollback() and onEditRollback), every cause is 'direct', and a task that was changed and changed back is not listed.

interface SessionChanges extends ChangeSet {
readonly reason: 'session' | 'rollback';
readonly links: {
readonly added: readonly LinkModel[]; // links now present that were not at the start
readonly removed: readonly LinkModel[]; // links present at the start that are gone or changed
};
}

A link model has an id, a source, a target, a type, an optional lag, and link, your own Link object (absent for a link that came from task.dependencies).

One user action makes one change set, with every task it touched. One drag that moves a task and five followers is one change set with six entries.

Operation reason Runs onBeforeTaskChange What you receive
Drag of a bar, an edge, progress 'move', 'resize-*', 'progress' Yes tasksChange, once
updateTask(id, update) 'api' Yes tasksChange, once; the result has changeSet
undo(), redo() 'undo', 'redo' No tasksChange, once
edit.commit() 'session' No Returned as changes, not emitted
edit.rollback() 'rollback' No editRollback, once, instead of tasksChange
setTasks, setLinks No No tasksChange: replacing data is not an edit

Link changes have no change set. Creating a link runs onBeforeLinkCreate and emits linkCreate(link, id). Removing a link runs no hook and emits linkDelete(record).

For a committed change the events come in this order:

  1. dirtyChange and historyChange, when those flags flipped.
  2. issues with source: 'change-set', when re-validation corrected or dropped something.
  3. tasksChange, exactly once.
  4. For every change in it, taskDatesChange when start or endExclusive changed and taskProgressChange when progress changed. They carry the TaskRecord and Dates.

A change that turns out to be empty, because a hook removed every change or the values are already the current ones, emits no tasksChange, and the call resolves { status: 'unchanged' }. If a listener starts another change, the new change is applied at once, but its events wait until all the events of the running one have been emitted.

const gantt = createGantt(container, {
tasks,
links,
onTasksChange: (changeSet) => {
console.log(
changeSet.reason,
changeSet.changes.map((change) => change.id),
);
},
});
const result = await gantt.updateTask('design', { progress: 50 });
if (result.status === 'committed') console.log(result.changeSet.changes.length);

In React onTasksChange is a prop of <Gantt> with the same argument.

A before-hook is a function you pass as an option (a prop in React). The chart calls it after it has computed a change and before it commits it. There is one function per hook; setOptions swaps it. A hook sees the world as it is going to be, and answers.

It receives one frozen argument, a BeforeTaskChangeContext:

Field Meaning
changeSet The change set about to be committed, already re-validated: every value is aligned to the granularity.
reason changeSet.reason, for convenience.
conflicts changeSet.conflicts: what the change would cause, see Propagation and conflicts.

It answers with a BeforeTaskChangeResult, or a promise of one:

Answer Effect
nothing, undefined or true Allow. The change is committed.
false Cancel. Nothing changes and no tasksChange fires. updateTask resolves { status: 'cancelled', reason: 'hook' }; a drag snaps back.
a ChangeSet Rewrite. It replaces the change set and is re-validated like any other (aligned, unknown and locked tasks dropped, conflicts recomputed). A missing reason keeps the old one.
a Promise of any of the above The same, after it settles.
it throws, rejects, or answers anything else Cancel with an error. updateTask resolves { status: 'cancelled', reason: 'error', error } and the chart emits error with source: 'hook' and name: 'beforeTaskChange'.

“Anything else” is a string, a number, null or an object that is not a change set. The error is a TypeError that names what the hook answered.

A rewrite replaces the whole change set, including the propagated tasks. If you change one task’s dates and keep the other entries as they are, the successors still stand where the original propagation put them. To get a consistent result, either cancel, filter the entries (keeping only cause === 'direct' turns propagation off for that gesture), or compute a new change set with propagate, as the clamp example below does. The re-validation drops a change whose after equals the current values, takes before from the model whatever you wrote, and reports what it corrected as issues (misaligned, end-before-start, locked-task, unknown-task, …). They are in the result’s issues and in the issues event with source: 'change-set'.

It receives a frozen BeforeLinkCreateContext:

Field Meaning
link The link to create, as given (or a copy with a free id, when its default id is taken).
id Its id: link.id, the default source:type:target, or the first free ...#2.
wouldCreateCycle true when the link would close a cycle of links.

It answers false to cancel, or nothing or true to allow, also as a promise. A link that would close a cycle is rejected whatever the hook answers; the hook is told so that it can explain why. A throw or rejection cancels the link and emits error with name: 'beforeLinkCreate'. The calls addLink and the link handle of the UI both run this hook. addLink resolves with the status 'created', 'cancelled' (with reason: 'hook') or 'rejected' (with a reason).

Operation Hook
A drag (move, resize, progress), updateTask onBeforeTaskChange
Drawing a link, addLink onBeforeLinkCreate
removeLink, the link menu’s remove action none
undo(), redo(), edit.commit(), edit.rollback() none
setTasks, setLinks, setOptions none

Undo and redo restore a state the hooks already accepted, and a veto would leave the history out of step with the data. A rollback is a cancel, and a cancel is never vetoed. editing: false does not matter here: it stops gestures, while hooks run for every drag that does happen and for updateTask.

A hook that returns a promise keeps the chart waiting for as long as the promise does. There is no timeout. Meanwhile:

  • The change being confirmed is shown as the draft: the dropped bar and its followers stay where the user left them.
  • The chart is busy. getSnapshot().busy is true; a new drag is refused (onEditRefused, reason: 'busy'); updateTask, addLink and removeLink resolve { status: 'busy' }; edit.begin(), commit() and rollback() and the history return { status: 'busy' }.
  • When the promise settles: allowed, the change is committed and the busy flag clears; refused, the draft is removed and the bars snap back.
  • destroy() ends the wait. The call resolves { status: 'cancelled', reason: 'disposed' } and a late answer is ignored.

A hook that never settles leaves the chart busy for good. If the answer comes from a person or a network, race it against a timer:

const timeout = (ms: number) => new Promise<false>((resolve) => setTimeout(resolve, ms, false));
onBeforeTaskChange: (context) => Promise.race([askUser(context), timeout(30_000)]),

A synchronous hook is not pending at all: the whole commit happens inside the call.

Inside an edit session every drag and every updateTask still runs the hook, as it does outside one. A change a hook cancels never reaches the session. The session’s own commit() and rollback() do not run hooks. A hook that is pending makes begin(), commit() and rollback() return { status: 'busy' }.

The conflicts say what the change would cause. Cancel when a bar would start or end on a non-working day. A progress drag does not move the bar, so let it through.

const gantt = createGantt(container, {
tasks,
links,
onBeforeTaskChange: ({ reason, conflicts }) => {
if (reason === 'progress') return true;
const onDayOff = conflicts.some(
(conflict) => conflict.type === 'non-working-start' || conflict.type === 'non-working-end',
);
if (onDayOff) showToast('That would land on a day off.'); // your UI
return !onDayOff; // false cancels
},
onError: ({ error }) => console.error(error), // a throwing hook is cancelled silently otherwise
});

In React the same function is the onBeforeTaskChange prop of <Gantt>, and onError is a prop too. A handler may close over state: it is never stale.

Resizing the end of a task must not make it longer than two weeks. Rewriting one entry would leave the successors where the longer edit put them, so run the propagation again with the clamped end:

import { propagate } from '@ganttlane/core';
import type { DateTimeMs } from '@ganttlane/core';
import { createGantt, type Gantt } from '@ganttlane/dom';
const TWO_WEEKS = 14 * 24 * 60 * 60 * 1000;
const gantt: Gantt = createGantt(container, {
tasks,
links,
onBeforeTaskChange: ({ changeSet }) => {
if (changeSet.reason !== 'resize-end') return true;
const edited = changeSet.changes[0]; // the edited task is always first
if (edited === undefined) return true;
const latest = edited.after.start + TWO_WEEKS;
if (edited.after.endExclusive <= latest) return true; // short enough: allow
const { state } = gantt.core.getSnapshot();
return propagate(
{ kind: 'resize-end', id: edited.id, endExclusive: latest as DateTimeMs },
{ ...state.derived, options: state.settings.propagation },
);
},
});

The answer is a full change set with the successors recomputed. Dates inside the core are branded numbers, hence the cast. updateTask with reason: 'api' would need the same check if you want the rule to hold for code too.

Ask the user before a change that leaves conflicts. The hook returns a promise, and the chart waits with the bars where the user dropped them.

function ask(message: string): Promise<boolean> {
return new Promise((resolve) => {
const dialog = document.createElement('dialog');
const text = document.createElement('p');
text.textContent = message;
const keep = document.createElement('button');
keep.textContent = 'Keep';
const discard = document.createElement('button');
discard.textContent = 'Discard';
dialog.append(text, keep, discard);
const done = (answer: boolean): void => {
dialog.remove();
resolve(answer);
};
keep.addEventListener('click', () => done(true));
discard.addEventListener('click', () => done(false));
dialog.addEventListener('cancel', () => done(false)); // Escape
document.body.append(dialog);
dialog.showModal();
});
}
const gantt = createGantt(container, {
tasks,
links,
onBeforeTaskChange: async ({ conflicts }) => {
if (conflicts.length === 0) return true;
return ask(`This change leaves ${conflicts.length} conflict(s). Keep it?`);
},
});

onBeforeLinkCreate sees the link before it exists. Here only tasks of the same team may be linked, read from the data payload of the tasks:

interface Meta {
team: string;
}
const gantt: Gantt<Meta> = createGantt<Meta>(container, {
tasks,
links,
onBeforeLinkCreate: ({ link }) => {
const from = gantt.getTask(link.source)?.task.data?.team;
const to = gantt.getTask(link.target)?.task.data?.team;
return from === to;
},
});
const result = await gantt.addLink({ source: 'design', target: 'build' });
// { status: 'created', ... } or { status: 'cancelled', reason: 'hook' }
  • Do not start a change from inside a hook. The chart is pending while the hook runs, so updateTask returns { status: 'busy' }. Answer with a rewritten change set instead.
  • Do not mutate the context. The change set is frozen. Build a new object.
  • Conflicts are about the changed tasks. conflicts lists what the edit can have caused, including conflicts that were already on a task it moved. A progress drag on a bar that already starts on a Saturday carries that conflict.
  • A replacement must stand alone. It is the whole change set. Keep the propagated entries, or recompute with propagate.
  • A hook does not guard code that skips it. setTasks and history steps pass no hook. Put a rule that must hold everywhere in your data layer as well.