Progress

Every bar has a done part: progress is a percentage of its length, and the handle at the foot of the done part is how you change it by hand. Moving a bar keeps its percentage; resizing it asks a question, because the bar is now longer or shorter: what stays, the part that is done or the part that is left? task.progressAnchor answers it. This chart has the same bar twice, with the answer 'start' (the default) and 'end', a bar in a colour of its own, and a box that decides whether the handle skips weekends.

Terminal window
pnpm add @ganttlane/dom # vanilla
pnpm add @ganttlane/react react react-dom # React
View on GitHub
data.ts
import type { Link, Task } from '@ganttlane/core';
// 2026-03-09 is a Monday: Build crosses a weekend (14 and 15 March). Progress is a percentage of
// the length of the task, `0` to `100`; a task without `progress` has none done.
export const tasks: Task[] = [
{ id: 'design', name: 'Design', start: '2026-03-09', end: '2026-03-13', progress: 100 },
// The same bar twice, with the same 50 % done, to compare what a resize does to the progress.
// `progressAnchor` says what a resize keeps: the part that is done (`'start'`, the default) or
// the part that is left (`'end'`).
{
id: 'build-start',
name: 'Build · anchor start',
start: '2026-03-09',
end: '2026-03-20',
progress: 50,
},
{
id: 'build-end',
name: 'Build · anchor end',
start: '2026-03-09',
end: '2026-03-20',
progress: 50,
progressAnchor: 'end',
},
// The done part is painted in the task's own colour (`--gantt-bar-progress-color`).
{
id: 'review',
name: 'Review',
start: '2026-03-16',
end: '2026-03-20',
progress: 60,
progressColor: '#e8590c',
},
// Counted in working days: the weekend is not part of the length, so its progress is not either.
{
id: 'qa',
name: 'QA',
start: '2026-03-18',
duration: 7,
durationMode: 'working',
progress: 40,
},
{ id: 'launch', name: 'Launch', start: '2026-03-23', end: '2026-03-27' },
];
export const links: Link[] = [];

Files

  • data.ts: six tasks with their progress, progressAnchor and progressColor.
  • options.ts: scheduling.skipNonWorkingDays.progress and the day column.
  • helpers.ts: the sentences of the status line.
  • vanilla.ts and react.tsx: the chart, a box and a reset button.

Options

Option Value What it does
task.progress 0 to 100 How much of the bar is done
task.progressAnchor 'end' on one Build What a resize keeps: the done part ('start', default) or the remainder
task.progressColor '#e8590c' on Review The colour of the done part (--gantt-bar-progress-color)
scheduling.skipNonWorkingDays.progress true The handle skips the days off (default true; the box)
viewModes { day: { pxPerDay: 30 } } A narrower day column than the default 40 px, so that the plan fits
scroll.initial 'first-task' Opens on the plan; the default, 'today', is far from these dates
scroll.align 0.08 A margin to the left of the first task (a fraction of the width), see the notes
onTasksChange a function (in the example) One ChangeSet per change; its reason is what the change was
onTaskProgressChange a function (in the example) Called with the TaskRecord and the new progress of a task whose progress changed

What to try

  • Drag the progress handle of Design, Review or any bar: it appears at the foot of the done part when you hover the bar. The status line says what the progress is now and the date the done part reaches.
  • Drag the right edge of both Build bars two days to the right. They had 50 % of 12 days done. Build · anchor start keeps the six days that are done, so the percentage drops (six of 14, 43 %). Build · anchor end keeps the six that are left, so the percentage rises (eight of 14, 57 %). Drag the edge two days to the left and the two swap sides (60 % and 40 %).
  • Drag the left edge of both and it is the other way around. The done part of the anchor 'start' bar moves with its start edge, and that of the anchor 'end' bar stays where it is.
  • Move a bar. The percentage is kept, and the status line says the progress is as it was (onTaskProgressChange is not called).
  • Drag the handle of Build · anchor start back to a weekday, and then forward onto the Sunday. With the box ticked the boundary jumps over the days off, to the Monday after them (58 %); with it unticked it rests on the Sunday (50 %). Going the other way it would jump to the Saturday.
  • Do the same with QA. It counts working days, so its boundary never rests on a day off, with the box ticked or not: it stops at the start of the weekend.

Notes

  • A resize rebases the progress. With 'start' the done amount (in days, or in working days for a task that counts them) stays, and the percentage changes: progress × old / new. With 'end' the remainder stays: 100 − (100 − progress) × old / new. Shrinking a bar below what is done gives 100 %. The percentage is kept exact, not rounded, so repeated resizes do not drift; only the date of the boundary is aligned to the data step.
  • Events. A change is one ChangeSet (onTasksChange, with a reason: 'progress' for the handle, 'resize-start', 'resize-end', 'move', …). After it, onTaskProgressChange is called for each task whose progress changed, with its record: record.progress and record.progressDate, the date the done part reaches. There is no event called progressChange.
  • Skipping days off (scheduling.skipNonWorkingDays.progress) belongs to the handle. It is a field of the same object as move and resize, which the example leaves as they are (the object is replaced whole by setOptions, so the fields it leaves out are back to their defaults).
  • The colour. progressColor sets the custom property --gantt-bar-progress-color on the bar; color does the same for the bar itself. Both can be set in your stylesheet too.
  • A margin on the left. A drag that comes near an edge of the chart scrolls it (scroll.autoScroll), so a bar that starts at the very edge cannot be taken by its left edge without the chart moving under it. scroll.align: 0.08 leaves the first bars a margin.
  • Editing. editing: { progress: false } turns the handle off for the chart, and a task’s own editable does it for one task.
  • React. scheduling is passed to <Gantt> after the spread of options, from state: in React the props are the truth, so an option changed with setOptions on the ref would be overwritten by the next render.